Palma del Río – Andalucía (Spain) – Hybrid System = PAT + PV

  • Micro Hydro – PAT:
    – Installed as a by pass (DN250)
    – Within the valve chamber
    – Operational conditions
    – P=20 mca
    – Q=0.01 m3/s
    – P ~ 1,5 kW
    – Anual production: 3.2 MWh
  •  Photovoltaic Central – PV:
    – Installed on the roof top of the chambre
    – 2 pannels
    – P=0.6 kW
    – Anual production : 1.1 MWh